Questions we are asked about this
What is the difference between a switchboard and switchgear?
Both distribute a large service to feeders and panels. Switchboards are the common choice for mid-size commercial buildings; switchgear is heavier equipment, typically with draw-out breakers in separate compartments, used on larger or more critical services. The engineer of record picks which one the design calls for. Our guide what is switchgear explains the difference in more detail.
Should our building be 208Y/120 or 480Y/277 volts?
Smaller commercial buildings with mostly receptacle, lighting and kitchen loads usually go 208Y/120. Buildings with large mechanical plant, long feeder runs or warehouse-scale lighting usually go 480Y/277 with step-down transformers for 120-volt loads. The engineer decides with the utility, based on the load calculation.
Who applies to FPL for a new commercial service?
Usually the owner, developer or contractor opens the request through FPL's construction project portal, and the electrical contractor and engineer supply the load and equipment information. FPL says planning can take a few months, so the request should go in as soon as the load is known. Cities with their own utility, such as Homestead and Lake Worth Beach, have their own process.
When does a commercial service need CT metering?
When the service is larger than a self-contained meter can handle. FPL's Electric Service Standards set the cut-over point and say FPL furnishes the current transformers while the customer furnishes the approved enclosures and cabinets. The engineer and the utility confirm the metering arrangement for each project.
Why is our switchgear lead time so long?
Commercial distribution equipment is generally built to order after the engineer approves the shop drawings, so the lead time starts at release, not at the first quote. Late design changes can send it back through submittals. Get current lead times from the supplier at the time of order and hold the design steady once it is released.
Can a service upgrade be done without closing the building?
Most of the work can be done with the building live. The actual changeover needs a planned outage tied to the utility's disconnect and reconnect appointment, and critical loads may need temporary power for that window. See working without closing the business.
Does equipment in a flood zone have to be elevated?
Local floodplain rules and the building code set the requirement, and the building department with jurisdiction applies them. FEMA's guidance treats elevating or relocating service and distribution equipment as the most effective protection, and FPL requires access to meters raised to meet local flood rules. Your engineer should confirm the design flood elevation for the site.
Do you design the service or provide engineered drawings?
No. KRW Electric works with the engineer of record on design-assist and load planning, then installs and coordinates the work. Engineered drawings and studies come from the engineer.